Important Dates and Deadlines

Date

Event

June 18, 2015

Date on which preliminary approval of Settlement was granted.

December 22, 2015

  • In vehicles with more than 120,000 miles, date by which spark plugs must be replaced by an authorized Ford Dealer to be eligible for reimbursement.

  • Date by which letters sent to the Claims Administrator requesting exclusion from the Settlement must be postmarked.

  • Date by which objections to the Settlement must be filed with the Court and copies sent to the Parties' Counsel must be postmarked.

  • Date by which Notices of Intent to Appear at hearing must be filed with the Court and copies sent to the Parties' Counsel must be postmarked.

January 25, 2016, at 1:30 p.m.

Fairness Hearing to be held at the United States District Court for the Northern District of Ohio, Thomas D. Lambros Federal Building and U.S. Courthouse, Courtroom 351, 125 Market Street, Youngstown, Ohio 44503.

August 25, 2016

Deadline for submitting claims for Spark Plug Replacements performed before October 23, 2015

February 27, 2017

Deadline for submitting claims for Spark Plug Replacements performed on or after October 23, 2015